Phasing of electrical equipment. Three-phase electrical circuits - history, structure, features of calculating voltage, current and power Three-phase circuits and their main parameters

8.1.Basic concepts and definitions

Electrical equipment of three-phase current (synchronous compensators, transformers, power transmission lines) is subject to mandatory phasing before the first connection to the network, as well as after repairs, during which the order and rotation of phases could be violated.

In general, phasing consists of checking the phase coincidence of the voltage of each of the three phases of the switched-on electrical installation with the corresponding phases of the network voltage.

Phasing involves three significantly different operations. The first of them consists of checking and comparing the order of the phases of the switched-on electrical installation and network. The second operation consists of checking the phase coincidence of voltages of the same name, i.e., the absence of an angular shift between them. Finally, the third operation consists of checking the identity (color) of the phases whose connection is supposed to be performed. The purpose of this operation is to check the correct connection between all elements of the electrical installation, i.e., ultimately, the correct supply of conductive parts to the switching device.

Phase. A three-phase voltage system is understood as a set of three symmetrical voltages, the amplitudes of which are equal in value and shifted (the amplitude of a sinusoid of one voltage relative to the preceding amplitude of a sinusoid of another voltage) by the same phase angle (Fig. 8.1, a).

Thus, the angle that characterizes a certain stage of a periodically changing parameter (in this case, voltage) is called the phase angle or simply phase. When considering two (or more) sinusoidally varying voltages of the same frequency together, if their zero (or amplitude) values ​​do not occur simultaneously, they are said to be out of phase. The shift is always determined between identical phases. Phases are indicated in capital letters A, B, C. Three-phase systems are also represented by rotating vectors (Fig. 8.1, b).

In practice, a phase of a three-phase system is also understood as a separate section of a three-phase circuit through which the same current passes, shifted relative to the other two in phase. Based on this, the winding of a generator, transformer, motor, or three-phase line wire is called a phase in order to emphasize that they belong to a specific section of the three-phase circuit. To recognize equipment phases, colored marks in the form of circles, stripes, etc. are applied to equipment casings, busbars, supports and structures. Elements of equipment belonging to a phase A, painted yellow, phases V-v green and phase C-to red. Accordingly, the phases are often called yellow, green and red: g, h, k.

Thus, depending on the issue under consideration, a phase is either an angle characterizing the state of a sinusoidally varying quantity at each moment of time, or a section of a three-phase circuit, i.e., a single-phase circuit that is part of a three-phase circuit.

The order of the phases. Three-phase voltage and current systems may differ from each other in the order of the phases. If the phases (eg mains) follow each other in order A, B, C - this is the so-called direct phase order (see § 7.3). If the phases follow each other in order A, C, B - This is the reverse order of the phases.

The order of the phases is checked with an induction phase indicator of type I-517 or a phase indicator of the FU-2 type with a similar design. The phase indicator is connected to the voltage system being tested. The terminals of the device are marked, i.e. indicated by letters A,V, S. If the phases of the network coincide with the markings of the device, the phase indicator disk will rotate in the direction indicated by the arrow on the device casing. This rotation of the disk corresponds to the direct order of the network phases. Rotating the disk in the opposite direction indicates the reverse order of the phases. Obtaining the direct order of phases from the reverse is done by changing the locations of any two phases of the electrical installation.

Sometimes instead of the term “phase sequence” they say “phase sequence”. To avoid confusion, we agree to use the term “phase rotation” only when it is related to the concept of a phase as a section of a three-phase circuit.

Phase rotation. So, by phase alternation we should understand the order in which the phases of a three-phase circuit (windings and terminals of electrical machines, line wires, etc.) are located in space, if you start bypassing them each time from the same point (point) and carry out in the same direction, for example, from top to bottom, clockwise, etc. Based on this definition, they talk about alternating designations for the terminals of electrical machines and transformers, the colors of wires and busbars.

Phase coincidence. When phasing three-phase circuits, there are various options for alternating the designations of inputs on the switching device and supplying voltages of different phases to these inputs (Fig. 8.2, a, b). Options in which the order of phases does not match, or the order of alternation of phases of the electrical installation and the network, when the switch is turned on, leads to a short circuit.

At the same time, the only possible option is when both coincide. A short circuit between the connected parts (electrical installation and network) is excluded here.

By phase coincidence during phasing, this is precisely the option understood, when the same voltages are supplied to the switch inputs, belonging in pairs to the same phase, and the designations (colors) of the switch inputs are consistent with the designation of the voltage phases (Fig. 8.2, c).

A three-phase EMF (voltage) system is understood as a set of three symmetrical emfs, the amplitudes of which are equal in value and shifted (the amplitude of each emf relative to the previous amplitude of the other emf) by the same phase angle. In Fig. 1d shows a diagram of the simplest synchronous three-phase current generator. Windings, in. which induced alternating emfs are placed in stator slots, offset circumferentially by 120°. The terminals of the windings are assigned the designations “beginnings” of the ABS “ends” X, Y, Z, respectively. A direct current passes through the rotor winding, creating a magnetic field. When the stator windings intersect the magnetic field of the rotating rotor, a symmetrical system of three sinusoidal EMFs of the same frequency and amplitude, shifted in phase by 120°, is induced in them (Fig. 1.6). For one rotation of the rotor, which corresponds to the time period T, a full cycle of EMF changes occurs in each of the windings. When the rotor axis /- / intersects the turns of the stator winding, maximum EMF is induced in them. But since for the three stator windings this occurs at different times, the maximums of the induced EMF are not in phase, i.e. their amplitudes Ed, Eg, E are shifted relative to each other by 1/3 of the period, or 120° .
Phase. The angle characterizing a certain stage of a periodically changing parameter (in this case, EMF) is called the phase angle or simple phase. When considering together two (or more) sinusoidally varying EMFs of the same frequency, if their zero (or amplitude) values ​​do not occur simultaneously, they are said to be out of phase. The shift is always determined between identical phases, for example between the beginnings of sinusoids, as shown in Fig. 1.6, or between amplitudes. When two sinusoids are shifted in phase, one of them will lag behind the other in time. To determine which of the sinusoids is lagging, their origins are found, i.e., zero values ​​of the EMF during the transition from negative 6 values ​​to positive ones.

Rice. 1. Obtaining a three-phase symmetrical EMF system: 1 - stator; 2 - stator winding; 3 - rotor; 4 - rotor winding

In Fig. 1.6 beginnings are designated by the letters a, b, c. It can be seen from the figure that the beginning of one sinusoid (for example, the sinusoid passing through point b) is located to the right of the beginning of another (sinusoid passing through point a). This indicates that the sinusoid with the beginning at point b lags in time from the sinusoid with the beginning at point a. The sinusoid passing through point c lags even more behind, since its beginning is shifted by (2/3) T or 240° from the beginning coordinates (the moment when / = 0). We can equally say that a sinusoid with a beginning at point a is ahead of a sinusoid with a beginning at point b by (1/3) Tvi with a beginning at point c by (2/3) T.
In practice, the phase of a three-phase system is also understood as a separate section of a three-phase circuit through which the same current passes, shifted relative to the other two in phase. Based on this, the winding of a generator, transformer, motor, or wire of a three-phase line is called a phase in order to emphasize that they belong to a specific section of the three-phase circuit.
Phases are designated by capital letters A, B, C. But it is not always convenient to hang letter inscriptions on the equipment of stations and substations. Therefore, when painting equipment (for example, busbars and connecting busbars in closed switchgear), which is used for corrosion protection, dyes of different colors are used. The paint is applied along the entire length of the tires.
Phase A tires are painted yellow, phase B tires are green, and phase C tires are painted red. Therefore, the phases are often called Zh, 3, K. To recognize the phases of equipment, corresponding colored marks in the form of circles or stripes are applied to casings, insulator fittings, structures and supports.
Thus, depending on the issue under consideration, a phase is either an angle characterizing the state of a sinusoidally varying quantity at each moment of time, or a section of a three-phase circuit, i.e., a single-phase circuit that is part of a three-phase circuit.
The order of the phases. The order in which the EMF in the phase windings of the generator pass through the same values ​​(for example, through positive amplitude values) is called the phase order. Three-phase EMF systems may differ from each other in the order of the phases. If the generator rotor rotates in the direction shown in Fig. 1,c, then the phases will follow in the order A, B, C - this is the so-called direct order of the phases. If the direction of rotation of the rotor is reversed, the order of the phases will also change. The phases will pass through the maximum values ​​in the order A, C, B - this is the reverse order of the phases.
Sometimes instead of the term “phase sequence” they say “phase sequence”. To avoid confusion, we agree to use the term “Phase Alternation” only when it is related to the concept of a phase as a section of a three-phase circuit.

Phase rotation.

So, by phase alternation we mean the order in which the phases of a three-phase circuit (individual line wires, windings and terminals of an electrical machine, etc.) are located in space, if you start bypassing them each time from the same point (point) and carry out in the same direction, for example, from top to bottom, clockwise, etc. Based on this definition, they talk about alternating the designations of the terminals of electrical machines and transformers, the colors of wires and busbars. In some cases, the order of phase alternation is strictly regulated. Thus, the order of alternating designations of the terminals of synchronous machines is taken to correspond to the order of phases for the established direction of rotation of the rotor. The rules for the construction of electrical installations (PUE) provide for closed switchgears the following order of alternation of painted busbars when they are located in a vertical plane: the top bus is yellow, the middle is green, the bottom is red. When the tires are located in a horizontal plane, the most distant tire is painted yellow, and the one closest to the service corridor is painted red. Branches from the busbars are made so that phase G is located on the left, phase K is on the right, if you look at the busbars from the service corridor (with three corridors in the switchgear, from the central one).
At open substations, the alternating colors of busbars and bypass busbars are oriented according to the power transformers. The tire phase closest to them is painted yellow, the middle phase is green, and the distant phase is red. Branches from the busbars are made in such a way that the bus of phase G is located on the left, and phase K on the right, when looking at the transformer from the side of the busbars.
Deviations from the above requirements for the order of alternating painting of RU PUE busbars are allowed as an exception in those individual cases when compliance with these requirements is associated with the complexity of installation or the need to install special supports for the transposition of overhead line wires.
Phase coincidence. When phasing three-phase circuits, there can be various options for alternating the designations (colors) of the inputs on the switching device and supplying voltages of different phases to these inputs. For simplicity of further reasoning, let us assume that the phasing voltages of two electrical installation bus systems have the same phase order A, B, C and Ax, Bi, C|. Under this condition, the phases of the same voltages may coincide, and the order of alternating input designations at the switch may not coincide (Fig. 2, a) or, conversely, with the same order of alternating input designations, the phased voltages may be shifted in phase (Fig. 2 , b). The rotation of stress vectors of the same name relative to each other can be not only at an angle of 120°, as shown in Fig. 2.6, but at any angle divisible by 30e, which is typical for transformers with different winding connection groups. In both of these cases, turning on the switch inevitably leads to a short circuit.
At the same time, it is possible that both coincide (Fig. 2, c) - A short circuit between the connected parts of the installation is excluded here.
By phase coincidence during phasing we mean precisely this case, when at the switch inputs located opposite each other and belonging to the same phase, the like voltages of the two parts of the installation coincide in phase, and the designations (colors) of the switch inputs are coordinated with the corresponding voltage phases and have the same alternation order.
Vector image of sinusoidally varying EMF (voltages, currents). Periodically changing sinusoidal quantities are depicted as sinusoids (Fig. 1.6) and rotating vectors - directed segments of a straight line (Fig. 1c).

Rice. 2. Options for mismatch (f. b) and coincidence (c) of phases of two parts of the electrical installation
For phase EMF vectors Ej4, Eg. Eq> shown in this figure, the directions are conventionally taken from the beginnings of the windings to their ends. The relationship between the sine curve and the rotating vectors is shown in Fig. 3. A sinusoid is obtained by projecting a rotating vector (equal on a given scale to the amplitude of the changing EMF) onto the vertical axis /-/, moved along the abscissa axis at a speed proportional to the frequency of rotation of the vector. The phase shift between two vectors, the beginnings of which are combined at one point, is determined by the angle V (Fig. 4). The lag of vector Eg from vector Ed is shown by the direction of the angle arrow (against the direction of rotation of the vectors).
It should be said that the concept of a rotating vector of EMF (voltage, current, etc.) in electrical engineering is somewhat different from the concept of a vector, say, force or speed in mechanics.


Rice. 3. Obtaining a sinusoidal graph when rotating a vector


Rice. 4. Image of two EMFs with sinusoids and vectors at different shear angles

If in mechanics vectors cannot be completely determined only by their values ​​without indicating the direction of their action in space, then in electrical engineering rotating vectors do not determine the actual direction of the quantities they represent in space. However, the combined arrangement of vectors rotating at the same frequency (for example, the EMF of three phases) on the diagram gives an idea of ​​the process occurring in an electrical circuit over time and allows one to make a quantitative assessment of the phenomena by performing elementary operations on the vectors.

Basic connection diagrams for three-phase circuits.

The windings of electrical machines (generators, synchronous compensators, motors) and transformers are connected in a star or triangle.
When connecting three generator windings into a star, their ends are combined into one point (Fig. 5, c), which is called zero (or neutral). The electromotive forces between the beginnings and the zero point of the windings are called phase EMF and are denoted Ed, Eg, Ee, or simply £ph. The electromotive forces between the phase terminals are called linear tn. They are obtained as the difference between the vectors of the corresponding phase EMF of the generator, for example Ed - Eg = Edd (Fig. 5, c).


Rice. 5. Connection of generator windings in a star (o), vector diagram of EMF (b), subtraction of phase EMF vectors (c)


Rice. 6. Connection of the generator windings with a triangle (e) and vector diagram of the EMF (b)
The order of the indices in the designation of linear EMF is not arbitrary - the indices are placed in order
subtraction of vectors: Ev-Ec = Evc\ Ec-El = ESA- Taking into account the given direction of rotation of the vectors, this arrangement of indices corresponds to the subtraction of the EMF vector of the lagging phase from the EMF vector of the leading one. As a result, the linear EMF vectors are always ahead of the decreasing phase vectors by 30°. The values ​​of linear EMF are \D or 1.73 times greater than phase ones, which is easy to verify by measuring the vectors on the diagram.
The connection of the generator windings with a triangle is shown in Fig. 6, o. Points A, B, C are common to each pair of phase windings. If there is no load connected to the generator terminals, then in the windings forming a closed circuit there is no current caused by sinusoidal EMF of industrial frequency, shifted relative to each other by (1/3) T, since at each moment of time the geometric sum of the EMF acting in the circuit triangle is equal to zero. You can verify this by examining the vector diagram in Fig. 6, b and the sinusoid of instantaneous EMF values ​​of a three-phase generator (Fig. 1, b).


Rice. 7. Change by 180° in the phase of the induced EMF when changing the terminal designations:
a - the phases of the EMF Ed and Ea coincide; b - EMF Ed and Eg are in antiphase

From Fig. 6, a it can be seen that when connected by a triangle, the linear wires extend directly from the beginning and end of the winding of each phase, therefore the phase EMFs are equal to the linear ones and coincide with them in phase. Note that at stations the windings of generators are usually connected in a star. The delta connection is extremely rare and only in turbogenerators of one type (TVS-30).
The windings of transformers, as well as generators, are connected in a star and triangle (a zigzag pattern is rare). The star circuit is often made with the zero point exposed. Schemes of connections in a star, in a star with a derived zero point and in a triangle in the text are usually designated by the letters U, Un and D, respectively. The high voltage (HV) windings of transformers are connected in U or D, regardless of the connection diagram of the power sources. The secondary windings of medium (MV) and low voltage (LV) are also connected in U or D.
Unlike generators, powerful transformers have a delta connection of at least one of its windings is normal)